“120 TPH Mobile Asphalt Batch Plant Delivered to Nigeria Within Just 2 Months”

Atlas compressed manufacturing to 40 days and commissioned the plant on site, with a 25% RAP system, while a parallel order was still in transit.

LocationNigeria
Project TypeInternational Export | Time-Critical Delivery
EquipmentAtlas MABP 120 Mobile Asphalt Batch Mix Plant with 25% RAP System

The Challenge

The client ordered two complete plants with a 45-day delivery deadline, a target that standard industry lead times make nearly impossible for even one plant.

An Ultra-Tight Deadline

The client’s project schedule left only 45 days to deliver, with no room to extend.

Standard Lead Times Fall Short

Typical manufacturing cycles run well beyond 45 days for a single plant, so a standard approach would miss the deadline.

Operational on Site, Not Just Delivered

The client needed the plant producing in Nigeria, not just shipped, so manufacturing, transport, installation and commissioning all had to fit into one tight window.

The Engineering Solution

Atlas rebuilt its production schedule around the client’s deadline and pushed its engineering team to peak output to deliver a complete plant on time.

The Engineering Solution 1
The Engineering Solution 2
The Engineering Solution 3

Plant & Equipment Supplied

1 × MABP 120 Mobile Asphalt Batch Mix Plant with an integrated 25% RAP system, fully installed and commissioned on site.

Compressed Manufacturing

Dedicated production scheduling and peak engineering output let Atlas complete one full plant in 40 days.

On-Site Installation & Commissioning

Atlas installed and commissioned the plant in Nigeria, and it reached full operation within 2 months of order placement.

The Victory

Project Outcomes

Atlas completed a full plant in 40 days, within the client’s 45-day window
The plant reached full operation on site within 2 months of order
Manufacturing, shipping, installation and commissioning completed within 2 months of order
The 25% RAP system supports sustainable, cost-effective production from day one

Performance Snapshot

MetricBeforeAfter
Manufacturing Time45-day delivery deadline1 complete plant in 40 days
Order to OperationFully operational on siteAchieved within 2 months
RAP Integration25% RAP systemIntegrated and commissioned
“We needed a plant on site quickly, and Atlas delivered. They built it, shipped it and commissioned it while our other order was still on its way. That speed made the difference for our project.”

Managing Director

Leading Road Construction Company, Nigeria

Facing a Deadline Your Current Supplier Can’t Meet?

Talk to Atlas engineers about fast-track manufacturing, mobile configurations and on-site commissioning for your next project.

Frequently asked questions.

How fast can Atlas build a mobile asphalt plant?

+
For this Nigeria project, Atlas completed one full MABP 120 plant in 40 days through dedicated production scheduling.

Can the MABP 120 run RAP?

+

How quickly can Atlas commission a plant on site?

+

Does Atlas supply plants to Africa?

+